Next phase of improvements to begin at Woking Road/ Bellfields Junction in Guildford

Work to upgrade the Woking Road/Bellfields Junction will begin on Wednesday 24 September. These highways improvements are part of our Weyside Urban Village (WUV) regeneration project.


What will the scheme deliver?

a new dedicated bus lane

an upgraded bus shelter

a new pedestrian footway

the existing crossing is also being upgraded to a safer, signal-controlled crossing


Why is the council making these improvements?

They are designed to make public transport more accessible and enhance pedestrian safety. They form part of a series of improvements that will:

mitigate the impacts of the new WUV development

enable people to travel more safely and efficiently, whether by foot, bike, bus, or car.


Traffic management during the works

Woking Road will remain open throughout the works. Two-way traffic will be maintained, although lanes will be narrower. Drivers are asked to take extra care when passing through the junction.

The existing bus lane near the junction will be temporarily closed.

The Stoke Bridges bus stop will be suspended. The nearest bus stop will be at School Close.

Pedestrian routes will be signposted with safe diversions in place.


Overnight road closures to resurface and repaint road markings will only be needed towards the end of the programme. The closures will be limited in duration. The 29-week work programme also allows for necessary infrastructure works by utility companies.


Cllr Tom Hunt, Deputy Leader and Lead Councillor for Economy and Place, said:

"This is the third improvement scheme we've delivered this year as part of the Weyside Urban Village regeneration. The new toucan crossing on Woking Road has already been completed, improvements to Bellfields Road are due to finish in October, and now we're starting work at Bellfields Junction.

"Each of these schemes is part of a joined-up package of improvements designed to work together. Once complete, they will improve road safety, keep traffic moving, and encourage more sustainable ways to travel. We're making real progress, and residents are seeing the benefits build as each stage is delivered."


May 21, 2026
Join us for our second community drop-in of 2026
February 20, 2026
community drop-in on Tuesday 24 February 2026 at St Peter’s Shared Church, Guildford, from 4pm to 7pm. Latest regeneration updates.
February 20, 2026
Work begins to transform two major junctions on A320 Woking Road Work to improve traffic flow, reduce congestion and enhance safety at the Woodlands Road and Moorfield Road junctions on Woking Road will begin on Wednesday 25 February 2026. These highways improvements are part of the wider Weyside Urban Village regeneration programme. Both junctions are being upgraded at the same time so the new traffic signals can operate together. This approach will help reduce exit blocking, ease congestion and improve journey reliability along this section of Woking Road. Woodlands Road junction improvements At the Woodlands Road junction on Woking Road, the existing roundabout will be replaced with a signal-controlled four-way junction. Co-ordinating this with the nearby Moorfield Road junction will help manage traffic more effectively and reduce delays, especially at busy times. Moorfield Road junction improvements At the Moorfield Road junction on Woking Road, a series of upgrades will increase capacity and improve traffic flow. A new northbound lane towards Woking will be added and the existing northbound lane will be converted to another southbound lane. Providing two southbound lanes approaching the junction will help to reduce congestion and make it easier for drivers to turn into the Slyfield Industrial Estate. A new signal-controlled pedestrian crossing will also be installed, alongside upgraded footways to improve safety and provide better connections with existing walking and cycling routes. Traffic management measures The scheme will be delivered in phases, starting with the removal of the Woodlands Road roundabout. This work will take place at night from Tuesday 2 March for around six weeks. A lane closure will be in place overnight for safety and lifted each morning to minimise disruption to daytime traffic. Councillor Vanessa King, Lead Councillor for Economy and Place said: “These improvements are another vital step in preparing the local road network for the Weyside Urban Village regeneration scheme. The new layouts will future‑proof the network for new homes and community facilities, while also helping to manage current traffic more effectively. Being committed to becoming a more environmentally responsible borough, we’re also placing strong emphasis on creating safer, more accessible routes for pedestrians and cyclists. “The Slyfield Industrial Estate is a major economic and commercial hub for Guildford, so improving access is essential for supporting local businesses. By delivering the works in carefully planned phases and managing traffic thoughtfully, we can keep the programme running safely while minimising disruption for residents, businesses and commuters.  “This project is ultimately about preparing the area for the exciting transformation ahead and ensuring that the right access is in place as new homes, infrastructure and facilities come forward.”