Woodlands Road Junction
HIGHWAYS AND TRANSPORT
Woodlands Road Junction Improvements
When is the work happening?
Works began on Wednesday 25 February 2026 and will take a year to complete.
Project details
The existing priority roundabout at Woodlands Road will be converted into a signalised junction. This improvement will:
- Better manage and coordinate traffic movements
- Work in conjunction with the nearby Moorfield Road junction
- Improve overall traffic flow
- Reduce delays along this section of Woking Road
- Improve journey reliability
Coordinated works with Moorfields Junction
Works at Woodlands Road junction are being delivered at the same time as improvements at Moorfields junction so that new traffic signals can operate together. Coordinating both junctions will help prevent junctions from becoming blocked and improve traffic flow along this section of the A320. You can read more about the related works on the Moorfields junction improvements page.
Programme and Phasing
The overall programme is expected to last approximately 12 months, subject to weather conditions. Works will be delivered in phases.
Phase 1
Start: Wednesday 25 February 2026
Working hours: 8:30am – 5pm (daytime)
Works: Site set-up and temporary footpaths
Phase 2a
Start: Monday 2 March 2026
Working hours: 9pm – 6am (night-time)
Works: Removal of the existing roundabout at Woodlands Road
Phase 2b
Start: Monday 2 March 2026
Working hours: 8am – 4pm (daytime)
Works: Pedestrian footpaths and utility diversions
Traffic Management
From Monday 2 March 2026, there will be night-time lane closures on this section of Woking Road between 9pm and 6am to remove the existing roundabout. These works are expected to last until the end of May 2026.
- Lane closures will be removed each morning
- Normal daytime traffic flow will resume daily
- Access to Slyfield Industrial Estate will be maintained at all times.
Please check advanced notice signs on the A320 for updates.
About the design
These improvements are part of the wider Weyside Urban Village plans, which were shared with the public in 2020. The final designs has been carefully reviewed and approved by the Highways Authority to make sure it is safe and works well for everyone. Detailed plans are available showing how the roads and spaces will look once the work is complete. They are technical drawings showing the layout, position of key structures, and access routes..
Latest news
If you would like to sign up for email updates on the transport projects, you can do so by clicking here and entering your email address