Moorfield Junction
HIGHWAYS AND TRANSPORT
Moorfield Junction Improvements
Why are these works taking place?
The works form part of the Moorfield Road junction improvement scheme, which supports the wider Weyside Urban Village regeneration. The improvements will increase capacity at the junction, improve traffic flow and make it safer and easier for people walking and cycling.
Why are some works taking place overnight?
Some activities, such as carriageway widening and resurfacing, need to take place overnight to minimise disruption to the high volume of traffic using Woking Road during the day. Overnight working also allows certain operations to be carried out more safely.
Will there be road closures?
Some phases of the works may require temporary road closures to allow activities to be carried out safely.
Where road closures are necessary, we will provide advance notice through roadside signage and updates on this webpage. Where properties are directly affected, we will also notify residents and businesses by letter where appropriate.
We will always aim to provide as much notice as possible, although some changes may be required at short notice due to factors such as weather, emergency utility works or unforeseen ground conditions
Work to improve the Moorfield Road junction has been ongoing since February 2026 as part of the wider Weyside Urban Village regeneration programme. The scheme will improve traffic flow, reduce congestion and enhance safety for all road users.
Latest update August 2026
Below is the latest programme of works.
Utility works on Woking Road
When: Monday 3 August to Friday 14 August 2026
Essential utility work will take place on Woking Road. During this period a temporary contraflow will be in place between Moorfield Road Junction and Woodland Road Roundabout on the lane towards Guildford town centre. This allows part of the road to be used as a safe working area while keeping the lane open for traffic.
Overnight carriageway widening works
When: Monday 17 August to Monday 21 September 2026
Closure from 8pm to 6am
A full overnight closure is required to widen the carriageway between the Moorfield Road traffic signals and the Jacobs Well Road junction. Temporary two-way traffic signals will be in operation overnight between 8pm and 6am and removed each morning at 6am. Access to and from Slyfield Industrial Estate will be maintained at all times.
About the work programme
Works began on Wednesday 25 February 2026 and are expected to continue until early 2027. Construction is being delivered in phases to minimise disruption wherever possible. Every effort will be made to complete the works as planned. However, the programme may be be affected by adverse weather, unforeseen ground conditions or emergency utility works.
Coordinated works with Woodlands Road
The Moorfield Road junction improvements are being delivered alongside works at the Woodlands Road junction. Coordinating the two schemes will enable the new traffic signals to operate together, helping to improve traffic flow and reduce the risk of congestion along this section of the A320.
Initial enabling works have now been completed, including the installation of temporary footpaths and the removal of the existing roundabout at Woodlands Road.
Phase 3 works at Woodlands Road are currently underway and are expected to continue until Wednesday 12 August 2026. You can find more information on the Woodlands Road Junction Improvements page.You can read more about the related works on the Woodlands Road Junction Improvements page.
Why we are doing the works
The Moorfield Road junction is being upgraded to improve traffic flow, reduce congestion and create safer, more accessible routes for people walking and cycling.
The scheme includes:
- A new northbound lane (Guildford towards Woking)
- Conversion of the existing northbound lane into a southbound lane (Woking towards Guildford)
- Two southbound approach lanes to improve access into Slyfield Industrial Estate
- A new signal-controlled pedestrian crossing
- Upgraded footways to strengthen connections to existing walking and cycling routes
About the design
These improvements are part of the wider Weyside Urban Village plans, which were shared with the public in 2020. The final designs has been carefully reviewed and approved by the Highways Authority to make sure it is safe and works well for everyone. Detailed plans are available showing how the roads and spaces will look once the work is complete. They are technical drawings showing the layout, position of key structures, and access routes.
Latest news
If you would like to sign up for email updates on the transport projects, you can do so by clicking here and entering your email address
